The village has three trees to be placed on properties north of the railroad tracks. One Snowdrift Crabapple and two American Hornbeams are looking to be placed in eligible space in the tree lawn or in close proximity to the street. If you are a property owner who is...
Main Street Bridge Delay
Recent Posts
Village Board Workshop Agenda
The Village Board will hold its regularly scheduled workshop on Monday, April 28, 2025 at 7pm in person at 49 State St./Village Court and via Zoom. Login credentials on the agenda. Action items are included in this agenda. Village Board Workshop 4-28-25 Updated...
Welcome Center 2025 – Ambassadors Wanted
Are you our next Brockport Ambassador? This is going to be an exciting year, as we commemorate the Erie Canal Opening in 1825! We are expecting more visitors this year due to the many celebrations happening along the canal. At the Brockport Welcome Center, we have the...
Village of Brockport New York Forward: Local Planning Committee Meeting
The Village of Brockport was selected as one of the Finger Lakes region’s recipients of a $4.5 million NY Forward grant. NY Forward is a statewide initiative that provides funding for high priority projects designed to boost local economies and transform village...
Update: Water Restored on Brockview
The water service on Brockview has been restored thanks to the Village of Brockport DPW. Thank you!
Brockview Area Water Main Break
Due to an accident by National Grid, the water main on Brockview Drive has broken. DPW is initiating work as soon as possible to repair and resolve the issue. The water will remain off in that vicinity until the repair is complete. Updates will be posted as...
Rumors had already been floating that the delayed-to-November bridge reopening was being delayed yet again. On August 23, the Village called a meeting with the NYSDOT to discuss the further delay. Mayor Blackman, Deputy Mayor Crane, Deputy Mayor Joyce Riley from Albion and Brockport Merchants Association representative Judy Andrew met at Village Hall with the three DOT engineers overseeing the project to learn about the delay and discuss its impact on the Brockport community, particularly village businesses.
The bridge was originally scheduled to open on September 6th, then postponed to November 22nd, and now early February. The Albion bridge, on the same contract and farther behind schedule, will reopen on December 19th. The contractor (Crane Hogan) has 480 days to complete each project without financial penalty. Failure to do so results in a fine of $7000/day (“liquidated damages”) which the NYSDOT deducts from what it pays the contractor.
The major problem causing the current delay is steel fabrication issues, including the lifting posts. The primary supplier for the structural steel—which must be US Manufactured—is a Buffalo New York firm. The contractor hires the supplier and the other subcontractors who all must be State approved. The contractor is ultimately responsible for keeping delivery on track. Subsequently, the DOT engineers have been working as a team with Crane Hogan and the main steel supplier, and Crane Hogan has also reached out to other suppliers. The DOT assured us that lessons learned from the greatly delayed Spencerport and Fairport bridge rehabilitations had been incorporated into the procedures for the Main Street bridge rehab. Unfortunately, none of the above will change the early February bridge completion date.
Here’s what’s happening currently on the Main Street bridge. The pit walls and floors on both north and south ends have been re-concreted; the counterweights (made of metal plates) are in place at the north end. The machinery beams will have to be put in place in notches carved out of the concrete walls. Those beams support the engine driving the bridge up, the cables, and large sheaves over which the cables run. Currently, the subcontractors are working offsite testing the recently manufactured lifting posts, which raise the bridge, and making the necessary adjustments and corrections. Trying to rehab a 110-year-old historic bridge, replace most of its parts, and assure it will have at least a 50-year life is challenging. In the words of one of the DOT engineers, “This project is a significant investment into the community and will provide a safe and reliable crossing of the canal for the next generation.”
Most deeply affected by the bridge delay are Brockport’s merchants. Some businesses have closed, moved, and come under new franchises. Sales are down. The holiday shopping season will take place with the bridge still closed. We encourage the Brockport community to support our downtown merchants: eat downtown, shop downtown, shop locally for the holidays. Mark your calendars for the Midnight Madness Halloween parade (October 25th). Black Friday (November 28th), Small Business Saturday (November 29), the Holiday of lights parade (December 1), and the Winter Market (December 14). Prepare for a grand downtown Main Street celebration when the bridge reopens in February 2025.