Main Street Bridge Delay

Recent Posts

Street Closures For Lights Parade

Main Street, from Five Corners to the Erie Canal, and surrounding side streets, will be closing at 3pm Sunday, December 8 for the Holiday Lights Parade and Fireworks. Streets will remain closed until approximately 7pm. Parade line-up will take place on streets between...

Newsletter Converting To Digital Edition

In order to be more green for the environment and for tax payer cost savings, the Winter 2024 Newsletter will be the last hard copy delivered to village residents. Going forward the newsletter will be offered electronically twice yearly.  Publication will be announced...

Village Board Meeting 12-2-24

The Village Board will hold its regularly scheduled meeting on Monday, December 2, 2024 at 7pm at Village Court, 49 State St. and via Zoom.  Login credentials on the agenda. VB Agenda Dec 2 202 WEST AVE -IMA

Notice of PBZBA Public Hearing and Meeting on December 9

The PBZBA will convene on Monday, December 9 at 6pm at 49 State Street.  Please see the meeting packet and information below. 2024-12-9 PBZBA redacted meeting pkt 24156 Sunflower Landing-Grading Plan 11-20-24 24156 Sunflower Landing-Site Plan-11-20-24

Brockport Symphony Orchestra Presents 15th Annual Holiday Pops Concert

Celebrating a Brockport tradition, the Brockport Symphony Orchestra will present their 15th Annual Holiday Pops Concert on Saturday, December 7, 2024, 7PM at the First Presbyterian Church of Brockport, 35 State Street in the Village of Brockport. Directed by Jonathan...

Brockport Invited to Interview Stage of NY Forward Round 3

The Village of Brockport is pleased to announce that they were selected to the participate in the second stage of the New York Forward, Round 3 Application process.  The 20-page application was completed cooperatively by grant writer Sean Kirby from R.J. Miller and...

Rumors had already been floating that the delayed-to-November bridge reopening was being delayed yet again.  On August 23, the Village called a meeting with the NYSDOT to discuss the further delay.  Mayor Blackman, Deputy Mayor Crane, Deputy Mayor Joyce Riley from Albion and Brockport Merchants Association representative Judy Andrew met at Village Hall with the three DOT engineers overseeing the project to learn about the delay and discuss its impact on the Brockport community, particularly village businesses.

The bridge was originally scheduled to open on September 6th, then postponed to November 22nd, and now early February.  The Albion bridge, on the same contract and farther behind schedule, will reopen on December 19th.  The contractor (Crane Hogan) has 480 days to complete each project without financial penalty.  Failure to do so results in a fine of $7000/day (“liquidated damages”) which the NYSDOT deducts from what it pays the contractor.

The major problem causing the current delay is steel fabrication issues, including the lifting posts. The primary supplier for the structural steel—which must be US Manufactured—is a Buffalo New York firm.  The contractor hires the supplier and the other subcontractors who all must be State approved.   The contractor is ultimately responsible for keeping delivery on track.  Subsequently, the DOT engineers have been working as a team with Crane Hogan and the main steel supplier, and Crane Hogan has also reached out to other suppliers.  The DOT assured us that lessons learned from the greatly delayed Spencerport and Fairport bridge rehabilitations had been incorporated into the procedures for the Main Street bridge rehab.  Unfortunately, none of the above will change the early February bridge completion date.

 

Here’s what’s happening currently on the Main Street bridge.  The pit walls and floors on both north and south ends have been re-concreted; the counterweights (made of metal plates) are in place at the north end.  The machinery beams will have to be put in place in notches carved out of the concrete walls. Those beams support the engine driving the bridge up, the cables, and large sheaves over which the cables run.  Currently, the subcontractors are working offsite testing the recently manufactured lifting posts, which raise the bridge, and making the necessary adjustments and corrections.   Trying to rehab a 110-year-old historic bridge, replace most of its parts, and assure it will have at least a 50-year life is challenging.  In the words of one of the DOT engineers, “This project is a significant investment into the community and will provide a safe and reliable crossing of the canal for the next generation.”

 

Most deeply affected by the bridge delay are Brockport’s merchants.   Some businesses have closed, moved, and come under new franchises.  Sales are down.  The holiday shopping season will take place with the bridge still closed.  We encourage the Brockport community to support our downtown merchants:  eat downtown, shop downtown, shop locally for the holidays.  Mark your calendars for the Midnight Madness Halloween parade (October 25th). Black Friday (November 28th), Small Business Saturday (November 29), the Holiday of lights parade (December 1), and the Winter Market (December 14).  Prepare for a grand downtown Main Street celebration when the bridge reopens in February 2025.